Hello guys,
I would like to know the feasibility for the following business requirement.
1. Currently in material master data , QM proc.active check box , QM control key, certificate type fields are inactive.
2. Hence in the PO line item the QA control key is blank. PO is released
3. Now I run MIGO transaction . In MIGO the field 'Certificate enclosed?' is not visible.
4. Due to this I do not get the PO line in QC55 report.
5. So now I maintain the Material master and the PO line item with the QM control keys.
6. Now when I try to create a certificate in QC51 I get an error "No certificate is required for the purchase order item".
Is it possible to avoid this error and create certificate from QC51 after MIGO ?
We can't change the flow as this is the live issue we are facing.
or by any means is it possible to bring the missing entry in QC55 output?